$12M Science Museum addition taking shape

A rendering of the Science Museum's forthcoming expansion.

Rendering courtesy of the Science Museum of Virginia.

The first addition to the Science Museum of Virginia’s campus in three decades is beginning to go vertical.

A construction crane loomed over the former Broad Street Station train depot last week as crews continued work on the steel frame of the future Dewey Gottwald Center, a community event and exhibition facility.

The 21,000-square-foot structure, on the Leigh Street side of the museum building, will serve as a location for the museum’s large-scale traveling exhibitions during the summer months and as a venue for community events the rest of the year.

Photo by Jonathan Spiers.

Photo by Jonathan Spiers.

“From September until April each year, we will host a number of special events for the community – both large and small – with the goal of continuing to expand our role as a community gathering space,” said Terri Rose, the museum’s communications director.

Construction started this spring and is slated to last a year, with the center scheduled to open in spring 2017.

The $12 million project was funded in part by a $4 million donation from the Herndon Foundation in honor of Floyd D. Gottwald Sr., the late patriarch of the Gottwald family and former chairman of Ethyl Corp., now NewMarket.

The donation was touted as the largest gift the museum had ever received. The rest of the project is covered by state capital funds.

The steel and glass structure – the first addition to the campus since The Dome astronomy facility and theater opened in 1983 – will feature a design that the museum describes as “an intentionally significant departure” from the original train station building designed by noted architect John Russell Pope. The sleek exterior will give the museum a new appearance from Leigh Street.

The interior will feature state-of-the-art media, audio and lighting systems, according to the museum. It will serve as a multipurpose space, accommodating large community events and smaller spaces for corporate meetings. The museum will charge fees to rent the facility for events.

The museum offered a second vantage point.

The museum offered a second vantage point.

The team behind the design included local architecture firm BCWH and New York-based firm Pfeiffer Partners. Locally based W.M. Jordan Company is the project’s construction manager.

Other local firms involved include W.O. Grubb Crane Rental, Dwight Snead Landscaping & Paving Co., B&B Electric, fire protection equipment supplier Fire-X, building product provider W.H. Stovall & Company, EMC Mechanical Services, commercial painters W.W. Nash & Sons, Walker’s Carpets & Flooring, and green building consultant Sustainable Design Consulting.

Also participating in the project are Charlottesville firm 2rw Consultants; concrete contractors IHC Ltd., of Norfolk; Lynchburg-based James River Industries; and Norfolk-based commercial painters E. Caligari and Son.

The museum is planning a black-tie kickoff event that will be followed by the opening of international traveling exhibition Da Vinci Alive, which will be making its North American debut.

The project got off to a rocky start late last year, when the Times-Dispatch reported the City of Richmond threatened a lawsuit in response to a planned construction fence between the museum and the adjacent Washington Redskins training camp facility.

And it isn’t the only museum-related construction on West Broad Street. Farther east, construction continues on VCU’s Institute for Contemporary Art.

A rendering of the Science Museum's forthcoming expansion.

Rendering courtesy of the Science Museum of Virginia.

The first addition to the Science Museum of Virginia’s campus in three decades is beginning to go vertical.

A construction crane loomed over the former Broad Street Station train depot last week as crews continued work on the steel frame of the future Dewey Gottwald Center, a community event and exhibition facility.

The 21,000-square-foot structure, on the Leigh Street side of the museum building, will serve as a location for the museum’s large-scale traveling exhibitions during the summer months and as a venue for community events the rest of the year.

Photo by Jonathan Spiers.

Photo by Jonathan Spiers.

“From September until April each year, we will host a number of special events for the community – both large and small – with the goal of continuing to expand our role as a community gathering space,” said Terri Rose, the museum’s communications director.

Construction started this spring and is slated to last a year, with the center scheduled to open in spring 2017.

The $12 million project was funded in part by a $4 million donation from the Herndon Foundation in honor of Floyd D. Gottwald Sr., the late patriarch of the Gottwald family and former chairman of Ethyl Corp., now NewMarket.

The donation was touted as the largest gift the museum had ever received. The rest of the project is covered by state capital funds.

The steel and glass structure – the first addition to the campus since The Dome astronomy facility and theater opened in 1983 – will feature a design that the museum describes as “an intentionally significant departure” from the original train station building designed by noted architect John Russell Pope. The sleek exterior will give the museum a new appearance from Leigh Street.

The interior will feature state-of-the-art media, audio and lighting systems, according to the museum. It will serve as a multipurpose space, accommodating large community events and smaller spaces for corporate meetings. The museum will charge fees to rent the facility for events.

The museum offered a second vantage point.

The museum offered a second vantage point.

The team behind the design included local architecture firm BCWH and New York-based firm Pfeiffer Partners. Locally based W.M. Jordan Company is the project’s construction manager.

Other local firms involved include W.O. Grubb Crane Rental, Dwight Snead Landscaping & Paving Co., B&B Electric, fire protection equipment supplier Fire-X, building product provider W.H. Stovall & Company, EMC Mechanical Services, commercial painters W.W. Nash & Sons, Walker’s Carpets & Flooring, and green building consultant Sustainable Design Consulting.

Also participating in the project are Charlottesville firm 2rw Consultants; concrete contractors IHC Ltd., of Norfolk; Lynchburg-based James River Industries; and Norfolk-based commercial painters E. Caligari and Son.

The museum is planning a black-tie kickoff event that will be followed by the opening of international traveling exhibition Da Vinci Alive, which will be making its North American debut.

The project got off to a rocky start late last year, when the Times-Dispatch reported the City of Richmond threatened a lawsuit in response to a planned construction fence between the museum and the adjacent Washington Redskins training camp facility.

And it isn’t the only museum-related construction on West Broad Street. Farther east, construction continues on VCU’s Institute for Contemporary Art.

Your subscription has expired. Renew now by choosing a subscription below!

For more informaiton, head over to your profile.

Profile


SUBSCRIBE NOW

 — 

 — 

 — 

TERMS OF SERVICE:

ALL MEMBERSHIPS RENEW AUTOMATICALLY. YOU WILL BE CHARGED FOR A 1 YEAR MEMBERSHIP RENEWAL AT THE RATE IN EFFECT AT THAT TIME UNLESS YOU CANCEL YOUR MEMBERSHIP BY LOGGING IN OR BY CONTACTING [email protected].

ALL CHARGES FOR MONTHLY OR ANNUAL MEMBERSHIPS ARE NONREFUNDABLE.

EACH MEMBERSHIP WILL ONLY FUNCTION ON UP TO 3 MACHINES. ACCOUNTS ABUSING THAT LIMIT WILL BE DISCONTINUED.

FOR ASSISTANCE WITH YOUR MEMBERSHIP PLEASE EMAIL [email protected]




Return to Homepage

POSTED IN Nonprofits

Editor's Picks

Subscribe
Notify of
guest

1 Comment
oldest
newest most voted
Inline Feedbacks
View all comments
Rebecca Aarons-Sydnor
Rebecca Aarons-Sydnor
7 years ago

Sustainable Design Consulting is proud to also be on the design team and is guiding the team towards a LEED Silver Certification.