City Council lays out timeline for Navy Hill decision; public hearings start tonight

NAVY HILL aerial 2 1

An aerial rendering of the proposed new arena and the surrounding buildings. (Courtesy navyhillrva.com)

Following weeks of work sessions, months of town hall meetings and hearings, and years of talk surrounding the project, Richmond City Council members can now see a light at the end of the Navy Hill tunnel.

At a committee meeting Monday evening, council formally received the final report from its appointed Navy Hill Development Advisory Commission, and laid out a timeline to conclude its own review of the $1.5 billion project. The process continues with a series of public hearings that starts tonight.

The timeline aims for a final vote on the proposal before March, according to a schedule announced by council President Cynthia Newbille.

“We have a timeline before us, with completion by the end of February,” Newbille said Monday after detailing steps to be taken in the meantime.

With the advisory commission’s review completed – its report generally giving a thumbs-down to the arena portion of the project, among other findings – those steps include:

• Council’s responses to that report, which Newbille asked members to submit by the end of this week;

• A closed session at council’s Jan. 13 meeting to compile a list of those responses, to be submitted to developer NH District Corp. (NHDC);

• A series of public hearings before council, to be held at 6 p.m. on Jan. 8 at Binford Middle School, Jan. 9 at Pine Camp Cultural Arts and Community Center, Jan. 14 at the Southside Community Services Center, Jan. 15 at Martin Luther King Jr. Middle School, and Jan. 16 in council chambers at City Hall;

• NHDC’s answers to council’s responses, which council is requesting from the developer by Jan. 20;

• Report from council’s hired third-party consultant Johnson Consulting, with initial report tentatively due Jan. 31 and a final presentation due Feb. 10;

• Further back-and-forth with NHDC, with council aiming for a final vote before March.

Advisory commission findings
Council spent most of the meeting going over the findings of the advisory commission, which presented its report after submitting it to council and posting it online Dec. 23.

coliseum-aerial

A 7-acre plot houses the city-owned Coliseum. (BizSense file photo)

A majority of the commission, according to the report, found that the publicly funded portion of the project – the proposed 17,500-seat arena that would replace the Coliseum and anchor the larger Navy Hill mixed-use development – would not be “a sound and reasonable public investment.”

While a majority supported using tax-increment financing to fund the arena, revenue from which would go toward paying off $300 million in bonds that the city would use to fund the facility, the commission determined that Navy Hill as a whole would pose a risk to the city’s general fund and public school funding.

The commission was mixed on other findings, such as the project’s impacts on other city programs and existing businesses. Members also took issue with the project’s tax district base value and revenue projections, development schedules and infrastructure cost estimates. A majority concluded the project’s overall costs have not been reasonably estimated, contending that more data is needed.

NHDC has provided additional information in response to the commission’s findings. Those documents and others related to Navy Hill have been compiled on the city’s website here.

Multilayered review
The advisory commission started reviewing the project in October, with a series of mostly weekend meetings culminating in four public hearings that were held in mid-December.

NavyHillAnnouncement1

Mayor Levar Stoney delivers a Navy Hill announcement last year. (Jonathan Spiers)

Council has held work sessions during that time to conduct its own review, with members also inviting NHDC to present the project at respective constituent meetings. Mayor Levar Stoney, who supports the project, held his own series of town hall meetings in November.

Late last year, council hired Johnson Consulting, a Chicago-based real estate and hospitality consulting firm, to provide a third-party analysis of the project, while NHDC announced it has lined up venue management company Spectra to manage the new arena.

NHDC has continued to rally supporters, through emails and other means, to attend public hearings, contact council members and volunteer in support of the project. And this week, ChamberRVA, which has endorsed Navy Hill, launched a radio ad campaign promoting the project.

The latest developments follow a busy year for Navy Hill. A recap of the project’s news in 2019 can be found here.

NAVY HILL aerial 2 1

An aerial rendering of the proposed new arena and the surrounding buildings. (Courtesy navyhillrva.com)

Following weeks of work sessions, months of town hall meetings and hearings, and years of talk surrounding the project, Richmond City Council members can now see a light at the end of the Navy Hill tunnel.

At a committee meeting Monday evening, council formally received the final report from its appointed Navy Hill Development Advisory Commission, and laid out a timeline to conclude its own review of the $1.5 billion project. The process continues with a series of public hearings that starts tonight.

The timeline aims for a final vote on the proposal before March, according to a schedule announced by council President Cynthia Newbille.

“We have a timeline before us, with completion by the end of February,” Newbille said Monday after detailing steps to be taken in the meantime.

With the advisory commission’s review completed – its report generally giving a thumbs-down to the arena portion of the project, among other findings – those steps include:

• Council’s responses to that report, which Newbille asked members to submit by the end of this week;

• A closed session at council’s Jan. 13 meeting to compile a list of those responses, to be submitted to developer NH District Corp. (NHDC);

• A series of public hearings before council, to be held at 6 p.m. on Jan. 8 at Binford Middle School, Jan. 9 at Pine Camp Cultural Arts and Community Center, Jan. 14 at the Southside Community Services Center, Jan. 15 at Martin Luther King Jr. Middle School, and Jan. 16 in council chambers at City Hall;

• NHDC’s answers to council’s responses, which council is requesting from the developer by Jan. 20;

• Report from council’s hired third-party consultant Johnson Consulting, with initial report tentatively due Jan. 31 and a final presentation due Feb. 10;

• Further back-and-forth with NHDC, with council aiming for a final vote before March.

Advisory commission findings
Council spent most of the meeting going over the findings of the advisory commission, which presented its report after submitting it to council and posting it online Dec. 23.

coliseum-aerial

A 7-acre plot houses the city-owned Coliseum. (BizSense file photo)

A majority of the commission, according to the report, found that the publicly funded portion of the project – the proposed 17,500-seat arena that would replace the Coliseum and anchor the larger Navy Hill mixed-use development – would not be “a sound and reasonable public investment.”

While a majority supported using tax-increment financing to fund the arena, revenue from which would go toward paying off $300 million in bonds that the city would use to fund the facility, the commission determined that Navy Hill as a whole would pose a risk to the city’s general fund and public school funding.

The commission was mixed on other findings, such as the project’s impacts on other city programs and existing businesses. Members also took issue with the project’s tax district base value and revenue projections, development schedules and infrastructure cost estimates. A majority concluded the project’s overall costs have not been reasonably estimated, contending that more data is needed.

NHDC has provided additional information in response to the commission’s findings. Those documents and others related to Navy Hill have been compiled on the city’s website here.

Multilayered review
The advisory commission started reviewing the project in October, with a series of mostly weekend meetings culminating in four public hearings that were held in mid-December.

NavyHillAnnouncement1

Mayor Levar Stoney delivers a Navy Hill announcement last year. (Jonathan Spiers)

Council has held work sessions during that time to conduct its own review, with members also inviting NHDC to present the project at respective constituent meetings. Mayor Levar Stoney, who supports the project, held his own series of town hall meetings in November.

Late last year, council hired Johnson Consulting, a Chicago-based real estate and hospitality consulting firm, to provide a third-party analysis of the project, while NHDC announced it has lined up venue management company Spectra to manage the new arena.

NHDC has continued to rally supporters, through emails and other means, to attend public hearings, contact council members and volunteer in support of the project. And this week, ChamberRVA, which has endorsed Navy Hill, launched a radio ad campaign promoting the project.

The latest developments follow a busy year for Navy Hill. A recap of the project’s news in 2019 can be found here.

Your subscription has expired. Renew now by choosing a subscription below!

For more informaiton, head over to your profile.

Profile


SUBSCRIBE NOW

 — 

 — 

 — 

TERMS OF SERVICE:

ALL MEMBERSHIPS RENEW AUTOMATICALLY. YOU WILL BE CHARGED FOR A 1 YEAR MEMBERSHIP RENEWAL AT THE RATE IN EFFECT AT THAT TIME UNLESS YOU CANCEL YOUR MEMBERSHIP BY LOGGING IN OR BY CONTACTING [email protected].

ALL CHARGES FOR MONTHLY OR ANNUAL MEMBERSHIPS ARE NONREFUNDABLE.

EACH MEMBERSHIP WILL ONLY FUNCTION ON UP TO 3 MACHINES. ACCOUNTS ABUSING THAT LIMIT WILL BE DISCONTINUED.

FOR ASSISTANCE WITH YOUR MEMBERSHIP PLEASE EMAIL [email protected]




Return to Homepage

POSTED IN Commercial Real Estate, Government

Editor's Picks

Subscribe
Notify of
guest

7 Comments
oldest
newest most voted
Inline Feedbacks
View all comments
Andrew reder
Andrew reder
4 years ago

Quote from article: the commission determined that Navy Hill as a whole would pose a risk to the city’s general fund and public school funding.

Quote from Stoney: The Commonwealth needs to do more for Virginia’s children, especially those growing up in poverty. The RPS adopted budget demands a lot from the City of Richmond.

I’m for growth but not at the expense of the youth.

James Gait
James Gait
4 years ago
Reply to  Andrew reder

Limiting growth is done at the expense of youth in the future.

Andrew reder
Andrew reder
4 years ago
Reply to  James Gait

Growth isn’t being limited. People are building, renovating and moving in all over the city without this project, not because of it potentially happening. I can thankfully afford the tax increases but many people can’t. When hard working people get broke, a faction tends to get more desperate, which more often than not, leads to more crime. Smaller projects in this city have been mismanaged, so I’m hesitant to trust them with more money.

James Gait
James Gait
4 years ago
Reply to  Andrew reder

Andrew, it seems as though many people against it seem to make these meandering vague arguments that really never land anywhere. You claim growth won’t be limited then you make a detour about rising assessments (which help schools). Then another stop about the plights of poverty. Speaking of poverty, wouldn’t it be nice if a new development brought hundreds of jobs closer to working class neighborhoods of Northside and North Church Hill? I don’t see how you tie either to your points to the argument that growth won’t be limited. Just because there are houses being built elsewhere doesn’t mean… Read more »

Michael Dodson
Michael Dodson
4 years ago
Reply to  James Gait

James higher tax base won’t mean higher tax revenue. I was at the 5th district meeting this week and even the representative from Navy Hill said tax revenue would not increase in the first 5-7 years and some projects/reviews say it will take 12 year or more. That would be another school generation before more funds come into play UNACCEPTABLE! And an interesting point was made, the Navy Hill said TIF revenue would be based off a $350 million dollar tower DOM bullt (the one complete) and the City assessment is just over $307 million. That is mean even before… Read more »

David Humphrey
David Humphrey
4 years ago
Reply to  Michael Dodson

Yes, it would take some time before additional revenues would be available for schools, but I would say that is better than them never being available if you do nothing.

David Humphrey
David Humphrey
4 years ago
Reply to  Andrew reder

One statement should not end the discussion. There may be ways to further mitigate that risk. These things often get revised many times before they come to a final agreement.