Henrico holds GreenCity developer in default for lack of progress, missed land payment

9.10R Henrico PC Aerial

An aerial rendering of the proposed $2.3 billion GreenCity development. (BizSense file)

The fate of Henrico’s massive arena-anchored GreenCity project is in question after its developers have been deemed by the county to be in default of agreements the two sides signed several years ago.

Default notices were recently issued to Green City Partners LLC, the development entity led by principals Susan Eastridge and Michael Hallmark that is driving the mixed-use portion of the 200-acre project along Interstate 95 between I-295 and Parham Road.

The default notices followed a nonperformance notice that the county sent the developers in mid-December, as well as a missed payment of over $5 million that was due last Friday to secure the site of the planned arena and supporting commercial development.

Friday’s scheduled payment was to be the last and largest of three annual installments for the developers to close on the former Best Products headquarters property, which makes up about half of the overall GreenCity site. Local firm Markel | Eagle is developing the other half, which is to consist of primarily single-family homes.

A purchase agreement between Green City Partners and Henrico’s Economic Development Authority includes a cure period that gives the developers 10 more days to make the $5.2 million payment, after which ownership of the property would revert back to the EDA. The cure period ends March 13.

County Manager John Vithoulkas said officials have been in conversation with Eastridge and Hallmark and have had two meetings since the notices were issued. He said the content of those meetings is confidential due to the ongoing cure period.

Calls to Eastridge and Hallmark were not returned Monday.

JohnVithoulkas

John Vithoulkas

While he called the alleged defaults “concerning” to the county, Vithoulkas said GreenCity remains a viable project that could be picked up by another developer, if it comes to that.

“Simply put, the developers have not performed to the terms of the agreements. We believe it’s time to move forward and return the Best Products property to the County, as stipulated in the agreements,” Vithoulkas said in a statement to BizSense.

“As a county, we remain bullish on the concept of a large, mixed-use development at this extraordinary location and believe it is perfectly suited to a privately funded arena for sporting events, concerts and other entertainment.”

Vithoulkas said the deals with Green City Partners and land ownership entity Green City Development Corp. were structured in a way that protect county taxpayers.

“We included extensive provisions to protect the interests of Henrico County and our taxpayers when we entered into agreements with Green City Partners and Green City Development Corporation,” he said.

Purchase agreement was changed, project schedule delayed

GreenCity property 9

The former Best Products headquarters building, which is to be repurposed as part of the GreenCity development. (File image courtesy Henrico County)

Green City Partners had made two prior payments that were considerably lower, at $500,000 each. The three payments were to add up to $6.2 million, the agreed-to total purchase price that was the amount the county paid for the 93-acre property in 2011.

The purchase agreement with Green City Partners had originally called for an initial payment of $5 million in 2023 and $1.2 million in 2024, with a possible extension for an additional year. The agreement was amended in 2022 in what county officials said was a change meant to firm up the closing date and show good faith for the project as it worked through the governmental process.

Well before Friday’s due date, however, concerns about the project had been brewing for months and were officially conveyed to the developers in a letter last July, in which Vithoulkas requested an update on the project’s progress and proof of steps taken to secure the site and line up financing.

The letter noted that since the Board of Supervisors approved zoning for GreenCity, the county had sold the Best Products property at cost, signed the development agreement, assisted in acquiring the residential portion of the site, acquired the neighboring Saint Gertrude athletic center property in support of GreenCity, started infrastructure improvements, and approved two community development authorities (CDAs) to help fund the development.

“By contrast, despite repeated assurances of imminent activity, GCP and GCDC have not obtained financing, submitted plans, or begun construction of any portion of the project,” the letter reads.

“As a result, GCP and GCDC are significantly behind the development schedule incorporated into the development agreement, and the property remains the same as it was at the time of the rezoning. Understandably, confidence has begun to wane in the ability of GCP and GCDC to begin (let alone complete) the project.”

In the notice of nonperformance sent in December, Vithoulkas reiterated that the developers had made no progress on construction and didn’t secure the residential portion of the property, known as Scott Farm, as they had originally said they would. Henrico would end up going in on the purchase of that land with Markel | Eagle, effectively splitting the $35 million price tag paid to the seller, an entity tied to local businessman Bill Goodwin.

GreenCity site plan 1

A site plan of the GreenCity project.

“Developers’ failure to place the Scott Farm Property under contract prior to rezoning dramatically increased the owner’s leverage and exposed Developers’ tenuous position,” the December notice reads. “To prevent the window from closing, the County and EDA partnered with a different developer and contributed over $18 million to the acquisition of the Scott Farm Property…”

The notice goes on to note quarterly meetings that were held with the developers in which they repeatedly extended schedules and projections for the project. It says the developers tied the lack of financing “to their inability to account for a hypothetical third-party development on the Best Products Property first introduced in 2022.”

“The third-party development is not within the control of Developers or the County, has never proceeded beyond preliminary discussions, and does not present a viable and reliable path to financing or funding Developer’s obligations,” the notice reads, adding that the development agreement makes it the developers’ “sole obligation to fund and finance the project, which cannot be avoided by the failure of a hypothetical third-party development to materialize.”

The notice adds that the developers’ estimates for proposed bridge loans varied from $5 million to $12 million, and proposed third-party debt and private equity varied from $50 million to $400 million.

To resolve the situation, the notice demanded that the developers provide their balance sheet and pro forma capital structure, unaudited finance statements for 2023 and 2024, details on planned equity contributions and projects necessary to support the CDA financing of the arena, lenders in talks to finance the projects, and an accounting of costs incurred and paid since the project’s inception.

The notice was copied to McGuireWoods attorney George Keith Martin, outside legal counsel for Henrico.

The Feb. 15 default notice reiterates the claims and notes the county “intends to pursue one or more remedies available to it” under the development agreement, including its repurchase option for the Best Products property. The agreement also requires that senior-level negotiations start within seven days of the default notice and conclude within 30 days.

Same developers behind Navy Hill, VCU Health project

12.2R GreenCity NavyHillDevelopers

Michael Hallmark and Susan Eastridge. (BizSense file photo)

The default notices come four years after Henrico announced GreenCity at the Best Products site in late 2020. The announcement followed the defeat earlier that year of Richmond’s Navy Hill plan, another arena-anchored project steered by Eastridge and Hallmark that would have replaced the shuttered Richmond Coliseum and redeveloped areas around it.

Eastridge and Hallmark also were the development team behind the ill-fated redevelopment of Richmond’s Public Safety Building that would have included a high-rise office tower for VCU Health. The demise of that project ended up costing the health system over $80 million in known exit penalties, tax payments and other costs.

While GreenCity was announced before the VCU Health project, Vithoulkas said the latter’s demise was a cause of concern for Henrico, which connected with Eastridge and Hallmark after Navy Hill was voted down by Richmond City Council.

Vithoulkas said he met the day after the vote with Tom Farrell, the late Dominion Energy CEO who was among several Richmond business heavyweights who had promoted Navy Hill and, Vithoulkas said, had vetted and vouched for the developers.

He said Henrico also vetted Eastridge and Hallmark and the GreenCity project before announcing it. Eastridge is CEO of Concord Eastridge, a Fairfax-based firm that focuses on public-private and mixed-use developments. Hallmark is a principal with Richmond-based Future Cities and has designed several arenas across the country.

Hallmark’s Future Cities also is planning Clay Street Station, a mixed-use rehab of an old power substation in Richmond’s Carver neighborhood.

Vithoulkas said the county was told during the process that the I-95 corridor in Central Virginia is the most underserved corridor in the country for an arena-anchored development like GreenCity. He said the need for a new arena and the attractiveness of the site for a large-scale development would remain.

“I fully expect that development will occur in this corridor,” Vithoulkas said Monday.

In addition to the 17,000-seat arena, which has been projected to cost $250 million, GreenCity is approved for 2.2 million square feet of office space, 280,000 square feet of retail, two 300-room hotels, 2,400 residential units and green space. The $2.3 billion project also would rehab the former Best Products headquarters building.

Venue management company ASM Global had signed on to develop and manage the arena and invest in other parts of GreenCity, including retail and hospitality uses that would support the arena and the larger so-called “ecodistrict” development.

The arena, which would theoretically replace the shuttered Coliseum as a regional venue, was most recently targeted for completion in 2026. Full buildout of the entire GreenCity project had been anticipated in 2033.

While those targets now appear to be in jeopardy, Vithoulkas reiterated that GreenCity remains a viable and needed project that would remain attractive to potential developers. He noted that Markel | Eagle is moving forward with developing the $400 million, 880-home residential section, and that designs are approved for two new bridge crossings over I-95 and planned sewer extensions under I-295 are on track.

Of the developer defaults, Vithoulkas said, “It’s disappointing on one hand, but I’m also optimistic that GreenCity is the kind of development that…I’m sure we’ll have another partner come forward at some point, if these developers aren’t able to literally take control of the property. I don’t know how they could because they are in a default situation.

“Right now what I think you have is a pause in a great project. I think you’ll see this go forward; this development team just couldn’t put it together,” he said. “I am optimistic as to the project itself.”

POSTED IN Government

Editor's Picks

Subscribe
Notify of
guest


34 Comments
oldest
newest most voted
Inline Feedbacks
View all comments
David Gammino
David Gammino
1 month ago

Well, all they need to do is convince Chesterfield to piss away a few hundred million and they will have accomplished the rare Metropolitan area Shyster Developer Triple Crown! Saw this coming as soon as this deal was announced, completely perplexed why an otherwise well run county would fall for the same playbook that cost VCU 80mm. I still can’t understand how they walked away with millions of $ from the VCU HEALTH deal.

Shawn Harper
Shawn Harper
1 month ago
Reply to  David Gammino

Could you explain to me what they are getting out of this? Since I am not paid to sift through all these details, it doesn’t seem like whatever they are doing is a good business.

Bruce Milam
Bruce Milam
1 month ago
Reply to  David Gammino

Dave, I still don’t believe we’ve found everything there is to know about that failed city relationship. The developers made a lot of money off very little contribution to the failed development. They were not properly vetted. So, where’s the money?

Michael Morgan-Dodson
Michael Morgan-Dodson
1 month ago
Reply to  Bruce Milam

No fooling on the vetting. So if you got to Future Cities website and portfolio it list all these RVA projects first (all now failed or failing) and then shows USA place in Tempe AZ. Voted on in 2014 but never built. A lot of the AZ stuff in early mid-2010s never got off the ground. The successful projects like Nokia, or the WaMu Theater, Comerica (now AZ Financial theater) are pushing 20-25 years old since they were built. And all I did was some googling and web page reading (on their own site).

Jim Hurlburt
Jim Hurlburt
1 month ago

Monorail!!
What’s it called?
Monorail!!!
Once again
Monorail!!!!!!

Will Weaver
Will Weaver
1 month ago
Reply to  Jim Hurlburt

Mono…D’OH!

Brett Themmore
Brett Themmore
1 month ago

I think everyone saw this coming. Why do municipalities continue to fall for these things and not put better protections in place for the public.

Don O'Keefe
Don O'Keefe
1 month ago

To all who think “The City” is the only municipality that struggles to get large projects done, please take note.

Will Weaver
Will Weaver
1 month ago

At least Henrico took steps to protect their interests, given Eastridge and Hallmark’s history and ended up not getting fleeced like Richmond and VCU Health System did.

Polgar Concertado
Polgar Concertado
1 month ago
Reply to  Will Weaver

Did Richmond get fleeced?

Will Weaver
Will Weaver
1 month ago

Actually, seeing as the Navy Hill project wasn’t actually approved by the voters, I guess Eastridge and Hallmark never had the chance to fleece Richmond. But VCUHS lost $80 million.

Kim Parson
Kim Parson
1 month ago

Stoney tried to shove these guys down our throat and thankfully City Council stood up for the people of Richmond. Someone act surprised by this default, please. And remember Stoney when it’s time to vote.

Will Weaver
Will Weaver
1 month ago
Reply to  Kim Parson

Stoney isn’t the mayor anymore, and this is Henrico County, not the city.

The developer defaulted but the contract allows Henrico County to repurchase the property, so it’s perfectly possible they find another developer to build the arena portion of the project.

Landon Edwards
Landon Edwards
1 month ago
Reply to  Will Weaver

No, Stoney isn’t the mayor anymore. But he’s hoping to become Lt. Governor. That’s the vote of concern.

Shawn Harper
Shawn Harper
1 month ago
Reply to  Landon Edwards

Indeed. He wanted to run for Governor, but someone probably told him that would be dumb.

Shawn Harper
Shawn Harper
1 month ago
Reply to  Will Weaver

Stepping Stoney never wanted to remain mayor but run for governor. It’s insane he was voted mayor, since he had zero Richmond connection but a lot of dark DNC money for inspirational TV ads.

Charles Frankenhoff
Charles Frankenhoff
1 month ago

Between this and the public safety building it would seem these developers have real issues in getting the job done. Unsurprisingly it seems like Henrico is handling this better than Richmond/VCU

Polgar Concertado
Polgar Concertado
1 month ago

Clearly it doesn’t look like Henrico is going to lose money like VCU, but I’m not sure I’d give them credit for handling this any better than Richmond – at least yet. Of course Henrico is trying to put a positive spin on this, but the location was and still is a big question mark. My guess is finding another developer (to build an arena) on this site will not be as easy as the county as making it sound.

Barry Coleman
Barry Coleman
1 month ago

Agreed, at the end of the day it’s another failed project. There is a common denominator, that being these particular developers. Just terrible!

Chris Williams
Chris Williams
1 month ago

Without commenting on the merits of the development (or lack thereof), it is disappointing that our region continues to lack a competitive, large-scale, arena for concerts, sports, meetings, etc. The last event at the coliseum was 2018. At this rate, we will go at least an entire decade without hosting a single large scale concert or sporting event. Richmond is the 44th largest metropolitan area in the United States. I’m not suggesting that the city/counties should be on the hook for the cost. However, I am recognizing the frustration that many local citizens have regarding the lack of this important… Read more »

Barry Coleman
Barry Coleman
1 month ago
Reply to  Chris Williams

You are correct. Especially when I travel around the country and see localities much smaller with first class facilities. It’s really puzzling but could point to the lack of regional cooperation. We have single localities each failing to get these types of projects done alone.

Lonzo Harris
Lonzo Harris
1 month ago

Make you wonder how many other states have had to go through this with this company.

John Bell
John Bell
1 month ago

One look at their websites and both companies seem pretty scammy. I’m curious just have thorough this “vetting process” was. Truly hope they did more than take Tom Farrell’s word for them

Last edited 1 month ago by John Bell
Justin Reynolds
Justin Reynolds
1 month ago

This is unfortunate but we all saw this coming. No one will ever build a development this large without major support from a locality and it’s too bad Henrico fell for it. It’s interesting how some of the usual voices who are hyper critical of the city are missing in the comments here—wonder why?!

Nick Feucht
Nick Feucht
1 month ago

Nice job with the reporting. Fair, fact based, thoughtfully connected to related past events. Thank you for your diligence. Please take over the RTD.

Polgar Concertado
Polgar Concertado
1 month ago
Reply to  Nick Feucht

I’m not so sure. Someone should have dug into and reported on the lack of movement on this project many months ago. This article almost comes across as a Henrico county press release.

Nick Feucht
Nick Feucht
1 month ago

Like the local daily newspaper……

Polgar Concertado
Polgar Concertado
1 month ago
Reply to  Nick Feucht

Or Richmond BizSense

Roy Locker
Roy Locker
1 month ago

Amazing reporting Jonathan. Amazing.

Barry Coleman
Barry Coleman
1 month ago

I was just wondering about this on yesterday. These developers seem to have a horrible track record. It seems to be time to move on. It doesn’t raise a lot of optimism that this project will come to fruition.

Dr. Abe C. Gomez
Dr. Abe C. Gomez
1 month ago

Very thorough article! I appreciate the detailed and rhetoric. Really brings the situation to light and ties in what may have lead to past failures with the developers.

Al Bosdell
Al Bosdell
1 month ago

Just revert, not revert back…….

Michael Boyer
Michael Boyer
1 month ago

Doswell,in Hanover Co would be a fantastic location to build an arena, double extra large at that!

Chris Yenson
Chris Yenson
1 month ago

It’s no surprise this project is stalled. In 2021, no one was considering the MMD would double or the Treasury rate would triple over the next 4 years.