Lawsuits seek to force sale of stalled ‘co-housing’ development site on Arthur Ashe Blvd.

cohousing2 Cropped

The development site as of last week. Construction began about a year ago. (Mike Platania photo)

The site of a stalled development on Arthur Ashe Boulevard could be sold in a court-ordered auction if a handful of recently filed legal challenges are successful. 

At least three lawsuits were filed in recent weeks by contractors who claim they’re owed millions of dollars for their work on D.C.-based Outlier Realty Capital’s unfinished 150-room “co-housing” project at 1101 N. Arthur Ashe Blvd.

Filed by general contractor Breeden Construction, electrician Tribble Electric, and materials firm White Cap Supply, the cases each name Outlier as a defendant and ask the court to force a sale of the project site to satisfy liens that were previously filed by the contractors.

In the works since 2020, the development was to bring nearly 150 bedrooms in 29 apartments in a co-housing concept in which tenants have their own bedroom and bathroom, while sharing common areas like kitchens and living rooms. 

Outlier broke ground at the site about a year ago, but work halted last summer, leading the project’s contractors to file a series of liens against the property. As of press time, only concrete columns have been built on the property and have sat untouched for months, jutting out from the ground with rebar poking out from their tops. 

With many of the liens still outstanding, the contractors have now filed the lawsuits seeking to enforce the liens. 

2.18R Cohousing rendering

A rendering of the planned co-housing development. (BizSense file)

Breeden, in its Dec. 27 suit in Richmond Circuit Court, claims it’s owed around $2.3 million for its work on the development and that “(Outlier has) failed and refused to make payment to Breeden for such labor and materials.”

The alleged non-payment of Breeden by Outlier has sent a ripple effect throughout the other related court filings. Because Breeden was the general contractor on the project, it was in charge of hiring the other subcontractors. 

On Jan. 30 Georgia-based White Cap filed a suit against both Breeden and Outlier, among others, seeking to enforce a lien. White Cap claims it’s owed around $80,000 for building materials like concrete, rebar and lumber that it supplied for the development. 

Just over a week later on Feb. 7, Tribble Electric filed its own lawsuit seeking to enforce its lien. Tribble, a local firm, claims Breeden owes it about $87,000 for electrical work and supplies. Tribble’s lawsuit notes that, “work was stopped due to non-payment by (Outlier),” and also alleges unjust enrichment against Outlier. 

Also named as defendants in each lawsuit is the development’s lender, Maryland-based EagleBank, and trustees Kenneth Gray and Timothy Annett.

Tribble, through its attorney Christopher Hill of The Law Office of Christopher G. Hill, declined to comment. White Cap and EagleBank’s attorneys did not respond to requests for comment, nor did Outlier managing partner Peter Stuart. 

Buckley Warden is a local attorney at ThompsonMcMullan with 15 years of experience in construction industry litigation. He’s not representing any of the parties in the Outlier cases, but explained how such lawsuits generally work. 

buckley warden

Buckley Warden

Warden said under Virginia law a party that files a lien has six months to “perfect” the lien by filing a lawsuit to enforce it. 

“The lien gives you collateral for you to actually be paid whatever it is that you are owed,” Warden said. “(But) you will lose that lien right if you do not file that lawsuit within six months of filing the lien.”

Even though the general contractor, subcontractors and suppliers name one another in their suits, Warden said it ultimately leads back to the property owner who started the ripple effect by not paying the general contractor and has to deal with clearing the liens. 

“The lien attaches to the real estate. That’s why it’s so powerful as a tool,” Warden said. 

Oftentimes after a lien is filed, the parties involved will reach a settlement agreement that includes having the liens satisfied, clearing the property’s title. Warden said it’s common for settlement negotiations to continue even after lawsuits to enforce a lien are filed. He said subcontractors and contractors aren’t always interested in litigating cases like these. 

“A lot of these people, I suspect with a project that size, are not actively pursuing the litigation. Maybe some of them are: lawyers are different, and they have different approaches,” Warden said.

 “The way I would approach it is you file to enforce your lien so you keep your lien right. That doesn’t mean you stop negotiating, or that you necessarily spend a bunch of money on any kind of discovery or litigation.…The last thing that most plumbers, electricians, carpenters, painters, want to do is spend a bunch of money on lawyers.”

If the lawsuits are successful and the court orders that the property be sold, Warden said it would be sold at auction, similar to a foreclosure auction.

Even though that outcome would generate some money that would be divvied up amongst the lien holders, Warden said he thinks auctions are “a bad outcome for everyone involved,” because it would likely sell for less than it would on the open market.

Outlier bought the land for $1.2 million in 2021. The 0.3-acre parcel was most recent assessed by the city at $1.4 million.

“You don’t want it sold on the courthouse steps. You won’t get as much for it,” he said. “Just like you don’t really want the court selling your home. You want your real estate agent to sell your home, you want it to be advertised and you want people to come look at it.”

That begs the question of what a potential buyer might be able to do with a partially built project.

walter parks

Walter Parks (Photo courtesy Scott Elmquist/Style Weekly)

Walter Parks, whose namesake architecture firm designed the Outlier building, said he thinks the pause in construction would not prevent the planned co-housing building from being built, and that if someone wanted to build something different on the site, the existing columns could be retained.

“If one could work within the footprint, you could build something different. You’d keep the footprint of the building basically, and you could rework what’s inside of it,” Parks said.

“I think it would be a challenge, but one of the things that we’ve done for years is renovate old buildings. You’re given a shell and you have to design a building inside of it. This is kind of like that. You’d have a given foundation plan and footprint, and you’d have to design a building around it.”

No hearings have been set in any of the lawsuits as of press time.

Subscribe
Notify of
guest


13 Comments
oldest
newest most voted
Inline Feedbacks
View all comments
Mark A. Olinger
Mark A. Olinger
1 month ago

Still sounds like post-graduate student housing, not a true co-housing project. Maybe when this gets shaken loose a real project can emerge.

Will Teeples
Will Teeples
1 month ago

I think the shared kitchen/common area model isn’t preferrable for someone like me (I cook a lot, and I detest a dirty kitchen), but I think there’s some validity to having it as a housing option for someone whose lifestyle can accommodate it.

Charles Frankenhoff
Charles Frankenhoff
1 month ago

It sounds like fancy SROs, yes, but I think there is a role for that in Richmond. Arguably more of a need than cohousing, which is a bit of a luxury product that seems to struggle for a clientele, neat as it’s goals are.

Charles Frankenhoff
Charles Frankenhoff
1 month ago

I hope it gets sold. It would be nice to see a building there, and current developer is unlikely to ever get moving again.
I’d assume the sitework could be re-used, and has some value to someone else.

Michael Morgan-Dodson
Michael Morgan-Dodson
1 month ago

You gotta love Walter’s comments; any architect should know that a builder or engineer is not gonna come behind and want to use someone else’s construction materials that they have no idea how it was done or how it was poured or if it was ever inspected by the city. Liability would not be worth the savings!

Any new buyer is gonna demolish the site clean even if they rebuild the same building and will start all over again.

Charles Frankenhoff
Charles Frankenhoff
1 month ago

no, this is commercial. Everything is inspected, engineered, and papered. The subs who put it in are some of the people filing, the only people missing are the money guys

C Jay Robbins
C Jay Robbins
1 month ago

For my own edification, why is this project failing? I would have thought it would be almost impossible to lose money building student or quasi student or student oriented housing in the area of VCU. Any history?

Charles Frankenhoff
Charles Frankenhoff
1 month ago
Reply to  C Jay Robbins

I don’t know, but my strong guess is financing – they were depending on cheap money to build it, and can’t make the project work at current rates. Probably a floating rate construction loan or a bridge loan timed out or some such

Bruce Milam
Bruce Milam
1 month ago

We could leave it as is and call it “Stonehenge West”? In all seriousness, this deal was dicey from the get-go with a scheme to lease four individual rooms in each unit but only one parking space to share. This arrangement works on the VCU campus with undergrads but it seemed so unlikely to succeed if marketed to unrelated professionals.

Tamara Martin
Tamara Martin
24 days ago

Dorms are bad enough when it comes to not knowing who you’ll end up with, but honestly, who would pay that much money to move in with 3 people you don’t know? Are there background checks, safety measures, guarantees that you aren’t getting the local meth dealer or crazy person that just got released from psych ward, or a sex offender?

Justin Reynolds
Justin Reynolds
23 days ago
Reply to  Tamara Martin

We already have some apartments like this in Richmond (ex. The James), and they mostly attract people who are new to Richmond. They help people make friends and they’re less expensive. I agree having so much shared space seems like an odd concept if you’re from here but they do serve a purpose.

David Martin
David Martin
24 days ago

There are other apartment projects in Richmond that have stopped construction and owe Subcontractors hundreds of thousands. This is not uncommon.

Jack Kay
Jack Kay
17 days ago

Typical scheister developer with no regard for the small business contractors or even the large affluent GC … only their pockets and their yacht payment . Tear it down and sell it off . Never team players only misers